Use this information to answer the following questions. Consider the following Activity-On-Node (AON) PERT project. The

Posted: Sun Jun 05, 2022 10:24 pm
by answerhappygod
Use This Information To Answer The Following Questions Consider The Following Activity On Node Aon Pert Project The 1
Use This Information To Answer The Following Questions Consider The Following Activity On Node Aon Pert Project The 1 (12.68 KiB) Viewed 47 times
Use This Information To Answer The Following Questions Consider The Following Activity On Node Aon Pert Project The 2
Use This Information To Answer The Following Questions Consider The Following Activity On Node Aon Pert Project The 2 (19.52 KiB) Viewed 47 times
Use this information to answer the following questions. Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. 4-5-6 4-5-6 345 5-6-7 3-4-5 E
Refer to the figure. What is the probability of not completing the project within 18 days? O 0.0668 O 0.4332 O 0.9332 O 0.4878 O 0.0122