Page 1 of 1

QUESTION 4 The project MUST be completed by the end of the year, no exceptions. This should be included in the project s

Posted: Sun Jun 05, 2022 10:18 pm
by answerhappygod
Question 4 The Project Must Be Completed By The End Of The Year No Exceptions This Should Be Included In The Project S 1
Question 4 The Project Must Be Completed By The End Of The Year No Exceptions This Should Be Included In The Project S 1 (37.53 KiB) Viewed 41 times
QUESTION 4 The project MUST be completed by the end of the year, no exceptions. This should be included in the project scope statement as a: a. Project constraint b. Project boundary c. Project acceptance criteria O d. Project assumption