Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like
Posted: Sun Jun 05, 2022 10:17 pm
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Time (weeks) Immediate Predecessor(s) Immediate Predecessor(s) Activity Activity (weeks) A 5 E 3 B B 7 F 5 B C 3 A G 10 C, E 3 A H 7 D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity A ES EF 5