QUESTION TWO Develop a material requirements plan for component H. Lead times for the end item and each component except

Posted: Sun Jun 05, 2022 10:06 pm
by answerhappygod
Question Two Develop A Material Requirements Plan For Component H Lead Times For The End Item And Each Component Except 1
Question Two Develop A Material Requirements Plan For Component H Lead Times For The End Item And Each Component Except 1 (46.68 KiB) Viewed 40 times
QUESTION TWO Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items. A C B (2) E (4) D (2) H (3) E (2) K D (2) H (3) K