The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Tim

Posted: Sun Jun 05, 2022 9:53 pm
by answerhappygod
The Following Table Of Probabilistic Time Estimates In Weeks And Activity Predecessors Are Provided For A Project Tim 1
The Following Table Of Probabilistic Time Estimates In Weeks And Activity Predecessors Are Provided For A Project Tim 1 (245.84 KiB) Viewed 52 times
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity a b Activity Predecessor A 5 7 -- B 8 10 A C 3 5 A D 9 12 B, C E 5 9 15 D Table 9.2 Reference: Ref 9-2 Using Table 9.2, the critical path for the project consists of activities Select one: A. A-B-C-D-E. B. A-B-D-E. C. A-B-C-D. D. A-B-C-E. 3 CO 4 LO 3