The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Tim
Posted: Sun Jun 05, 2022 9:53 pm
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity b a | m | A 3 5 7 B 10 C 5 D 12 E 15 Table 9.2 Reference: Ref 9-2 Using Table 9.2, the earliest start (ES) time for activity D is Select one: A. 18.33 weeks. B. 12.67 weeks. C. 21.67 weeks. D. 8.17 weeks. E 4265 ∞0 39 Activity Predecessor -- A A B, C D