Page 1 of 1

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Tim

Posted: Sun Jun 05, 2022 9:53 pm
by answerhappygod
The Following Table Of Probabilistic Time Estimates In Weeks And Activity Predecessors Are Provided For A Project Tim 1
The Following Table Of Probabilistic Time Estimates In Weeks And Activity Predecessors Are Provided For A Project Tim 1 (121.75 KiB) Viewed 54 times
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity b A B 10 C D E 15 Table 9.2 Reference: Ref 9-2 Using Table 9.2, the expected time to complete the project is Select one: OA. 21.67 weeks. B. 34.17 weeks. C. 33.23 weeks. D. 31.00 weeks. 3 GINA W 4 2 6 5 3 L 0039 525 12 Activity Predecessor -- A A B, C D