Question 3 Not yet answered Marked out of 1.00 Flag question The following table of probabilistic time estimates (in wee
Posted: Sun Jun 05, 2022 9:51 pm
Question 3 Not yet answered Marked out of 1.00 Flag question The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity a b A 3 5 7 B 4 8 10 с 2 3 5 D 6 9 12 E 5 9 15 Table 9.2 Reference: Ref 9-2 Using Table 9.2, the earliest start (ES) time for activity D is Select one: O A. 21.67 weeks. O B. 12.67 weeks. O C. 8.17 weeks. O D. 18.33 weeks. 3 Activity Predecessor -- A A B, C D