Page 1 of 1

Question 7 Not yet answered Marked out of 1.00 Flag question A project consists of the following activities: Activity A

Posted: Sun Jun 05, 2022 9:50 pm
by answerhappygod
Question 7 Not Yet Answered Marked Out Of 1 00 Flag Question A Project Consists Of The Following Activities Activity A 1
Question 7 Not Yet Answered Marked Out Of 1 00 Flag Question A Project Consists Of The Following Activities Activity A 1 (21.26 KiB) Viewed 25 times
Question 7 Not yet answered Marked out of 1.00 Flag question A project consists of the following activities: Activity A B Activity Predecessor --- A A B с F D,E Table 9.1 Reference: Ref 9-1 Using Table 9.1, the amount of slack associated with activity C is Select one: O A. 3 weeks. O B. cannot be calculated O C. 0 weeks. O D. 6 weeks. с D E Time (weeks) 5 8 3 7 6 10