Question 6 Not yet answered Marked out of 1.00 Flag question A project consists of the following four activities with ac

Posted: Sun Jun 05, 2022 9:50 pm
by answerhappygod
Question 6 Not Yet Answered Marked Out Of 1 00 Flag Question A Project Consists Of The Following Four Activities With Ac 1
Question 6 Not Yet Answered Marked Out Of 1 00 Flag Question A Project Consists Of The Following Four Activities With Ac 1 (17.63 KiB) Viewed 41 times
Question 6 Not yet answered Marked out of 1.00 Flag question A project consists of the following four activities with activity times in days: Activity Predecessor Time A 6 B A 5 с A 4 D B,C 8 Table 9.3 Reference: Ref 9-3 Using Table 9.3, the time to complete the entire project would be Select one: O A. 17 days. O B. 23 days. O C. 19 days. D. 11 days.