Page 1 of 1

Question 9 Not yet answered Marked out of 1.00 Flag question A project consists of the following activities: Activity A

Posted: Sun Jun 05, 2022 9:49 pm
by answerhappygod
Question 9 Not Yet Answered Marked Out Of 1 00 Flag Question A Project Consists Of The Following Activities Activity A 1
Question 9 Not Yet Answered Marked Out Of 1 00 Flag Question A Project Consists Of The Following Activities Activity A 1 (19.9 KiB) Viewed 33 times
Question 9 Not yet answered Marked out of 1.00 Flag question A project consists of the following activities: Activity A B с D E F Table 9.1 Reference: Ref 9-1 Using Table 9.1, the earliest start time for activity F is Select one: O A. 30 weeks. B. 13 weeks. O C. 14 weeks. O D. 20 weeks. Activity Predecessor --- A A B с D,E Time (weeks) 5 8 3 7 6 10