Question 4 Not yet answered Marked out of 1.00 Flag question The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity a m b Activity Predecessor A 3 5 7 B 4 8 10 A с 2 3 5 A D 9 12 B, C E 5 9 15 D Table 9.2 Reference: Ref 9-2 Using Table 9.2, the probability that the project will take longer than 33 weeks to complete is approximately Select one: O A. 0.19. OB. 0.32. O C. 0.68. O D. 0.81. IN LO 6