For the project described in the table below, show, step by step, how to reduce its duration. Activity times are in days
Posted: Sun Jun 05, 2022 9:34 pm
For the project described in the table below, show, step by step, how to reduce its duration. Activity times are in days. Indirect project cost is $2,000 per day. What is the optimal duration of the project? Activity Normal Time Crash Time Daily Crash Cost 2-3 7 5 $700 2-4 8 7 $1,500 3-5 6 $1,000 4-7 11 $1,700 4-6 4 $500 5 8 3