Page 1 of 1

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Tim

Posted: Sun Jun 05, 2022 5:10 pm
by answerhappygod
The Following Table Of Probabilistic Time Estimates In Weeks And Activity Predecessors Are Provided For A Project Tim 1
The Following Table Of Probabilistic Time Estimates In Weeks And Activity Predecessors Are Provided For A Project Tim 1 (136.26 KiB) Viewed 56 times
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) b Activity a Activity Predecessor 3 7 A 4 10 A B 2 5 A с 6 12 B, C 5 E 19 15 D Table 9.2 Reference: Ref 9-2 Using Table 9.2, the probability that the project could be completed in 34 weeks or less is approximately Select one: O A. 0.89. OB. 0.91. OC. 0.86. O D. 0.96. D m 5 8 B 9