The tabulation below shows development sampling results for a mine, which produces lead with silver as a by-product. Dev
Posted: Thu Jun 02, 2022 10:28 am
The tabulation below shows development sampling results for a mine, which produces lead with silver as a by-product. Development is sampled at 5m intervals Development Sections Lode width Density Lead Silver end sampled (cm) t/m^3 % g/t 11 32 5.62 14.1 27 7 41 4.89 10.8 31 9 21 6.62 16.3 42 14 37 5.15 12.4 30 Calculate for the four ends combined: 2.1 The average Lead value 2.2 The average Lode width 2.3 The average Density 2.4 The average Silver value ABCO А с D