Page 1 of 1

5. A project has the activities and activity times (days) listed below. Construct a network diagram for the project. Det

Posted: Mon May 30, 2022 6:11 pm
by answerhappygod
5 A Project Has The Activities And Activity Times Days Listed Below Construct A Network Diagram For The Project Det 1
5 A Project Has The Activities And Activity Times Days Listed Below Construct A Network Diagram For The Project Det 1 (25.96 KiB) Viewed 14 times
Please show every working please.
5. A project has the activities and activity times (days) listed below. Construct a network diagram for the project. Determine the probability that the project will be completed in 40 days or less. Expected time Standard deviation Activity 1-2 15 2 2-4 17 1 1-3 14 1.5 3-4 16 0.5