4. For the project described in the table below, show, step by step, how to reduce its duration. Activity times are in d

Posted: Mon May 30, 2022 6:10 pm
by answerhappygod
4 For The Project Described In The Table Below Show Step By Step How To Reduce Its Duration Activity Times Are In D 1
4 For The Project Described In The Table Below Show Step By Step How To Reduce Its Duration Activity Times Are In D 1 (26.17 KiB) Viewed 12 times
Please show every working thank you.
4. For the project described in the table below, show, step by step, how to reduce its duration. Activity times are in days. Indirect project cost is $2,000 per day. What is the optimal duration of the project? Daily Crash Activity Normal Time Crash Time: Cost 2-3 7 5 $700 2-4 8 7 $1,500 3-5 6 5 $1,000 4-7 11 8 $1,700 4-6 4 3 $500