Munson Manufacturing, in Gainesville, Florida, wants to arrange its four work centers so as to minimize interdepartmenta
Posted: Mon May 30, 2022 5:23 pm
Munson Manufacturing, in Gainesville, Florida, wants to arrange its four work centers so as to minimize interdepartmental parts handling costs. The flows and existing facility layout are shown in the figures below. Figure 1. Parts Moved Between Work Centers A B с D 420 500 200 350 0 0 0 Figure 2. Existing Layout A -30 B с -30 -30 H a) For the existing layout, the cumulative "load x distance" or "movement cost" = feet (enter your response as a whole number). ABCD D 2100 75 0 700