Please make sure to add end item.
Complete the following problem. Please find the data table in the Excel spreadsheet Homework 5.xls. I strongly recommend completing the problem in Excel. Consider the product structure diagram in the figure below. Given the available inventory for each of the components and the master production schedule for the end item and spares described in Homework5.xls, perform the explosion calculus to determine the planned order releases for components A, B and C. Assume that lot-for-lot scheduling is used throughout, and there are no scheduled receipts. Hint: Note that is required for both A and B. End Item A(2) 1 week B(1) 2 weeks C(1) 2 weeks D(2) 1 week C(2) 2 weeks E(3) 2 weeks