The project manager of Good Public Relations gathered the data shown in the following table for a new advertising campai
Posted: Mon May 30, 2022 4:51 pm
questions: 1. How long is the project likely to take? 2. What is the probability that the project will take more than 38 weeks? 3. Consider the path A-E–G-H–J. What is the probability that this path will exceed 38 weeks? 12 H
The project manager of Good Public Relations gathered the data shown in the following table for a new advertising campaign. TIME ESTIMATES (WEEKS) Activity Optimistic Most Likely Pessimistic Immediate Predecessor(s) A 8 10 12 START B 5 8 17 START C 7 8 9 START D 1 2 3 B E 8 10 A, C F 5 6 7 D, E G 1 3 5 D, E H 2 5 8 F, G I 2 4 6 G J 4 5 8 H K 2 2 2 Answer the following