Answer questions 5 to 9 using the diagram shown below The following project network diagram (activity times are in month

Posted: Mon May 30, 2022 4:39 pm
by answerhappygod
Answer Questions 5 To 9 Using The Diagram Shown Below The Following Project Network Diagram Activity Times Are In Month 1
Answer Questions 5 To 9 Using The Diagram Shown Below The Following Project Network Diagram Activity Times Are In Month 1 (33.22 KiB) Viewed 14 times
Answer questions 5 to 9 using the diagram shown below The following project network diagram (activity times are in months) represents Medro & Mariana's next project for opening a new branch for (M&M) The critical path is (7 Points) K X 6 M 7 Y 5 START a. A-X-Z-M b. A-X-K-M c. A-Y-Z-M d. A-Y-L-M e. None of the above K6 28 Z 8 L3 L 3 FINISH