Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a
Posted: Mon May 30, 2022 4:33 pm
statement? Budget Actual Percent Account Code Budget Earned PV UOM Quantity EV Quantity Complete Total To-Date SF 3,000 6,000 03110 Formwork 03210 Rebar Ton 6 900 1,600 03310 Place & Finish CY 640 Subtotal Slabs at grade 4,000 10 800 HII
Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true statement? Budget Actual Percent Account Code Budget Earned PV UOM Quantity EV Quantity Complete Total To-Date SF 3,000 6,000 03110 Formwork 03210 Rebar Ton 6 900 1,600 03310 Place & Finish CY 640 Subtotal Slabs at grade 4,000 10 800 HII
Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true statement? Budget Actual Percent Account Code Budget Earned PV UOM Quantity EV Quantity Complete Total To-Date SF 3,000 6,000 03110 Formwork 03210 Rebar Ton 6 900 1,600 03310 Place & Finish CY 640 Subtotal Slabs at grade 4,000 10 800 HII