the EV reporting for level of effort activities is based on the following

Posted: Mon May 30, 2022 4:32 pm
by answerhappygod
the EV reporting for level of effort activities is based on the following
The Ev Reporting For Level Of Effort Activities Is Based On The Following 1
The Ev Reporting For Level Of Effort Activities Is Based On The Following 1 (214.28 KiB) Viewed 26 times
Budget Earned Account Code PV EV 03110 Formwork 4,000 6,000 03210 Rebar 10 900 03310 Place & Finish 800 640 1,600 Subtotal Slabs at grade O a. EV (BCWP) is equal to actual cost (ACWP): no cost variations can exist EV (BCWP) is equal to quantity installed None of these choices O d. EV (BCWP) is equal to scheduled (BCWS); no schedule variations can exist O b. O c. UOM SF Ton CY Budget Quantity Total Actual Quantity To-Date 3,000 Percent Complete