6. In an assembly operation at a furniture factory, six employees assembled an average of 720 standard dining tables per

Posted: Mon May 30, 2022 4:15 pm
by answerhappygod
6 In An Assembly Operation At A Furniture Factory Six Employees Assembled An Average Of 720 Standard Dining Tables Per 1
6 In An Assembly Operation At A Furniture Factory Six Employees Assembled An Average Of 720 Standard Dining Tables Per 1 (18.06 KiB) Viewed 14 times
6. In an assembly operation at a furniture factory, six employees assembled an average of 720 standard dining tables per six-day week. What is the labor productivity of this operation? A 10 tables/worker/day B. 20 tables/worker/day C. 30 tables /worker/day D. 40 tables /worker/day E. 50 tables/worker/day