Write the steps of Line Balancing. From the table below, draw the 5 stations facility layout chart. If desired output ra
Posted: Mon May 30, 2022 4:11 pm
Write the steps of Line Balancing. From the table below, draw
the 5 stations facility layout chart. If
desired output rate is 3600 units/week then calculate the Cycle
time, Idle time, Theoretical minimum (#
of stations) and Efficiency.
Work Stations
A
B
C
D
E
F
G
H
I
Predecessor
-
A
A
B
B
C
C
D, E
F, G
Time (sec)
40
30
50
40
6
25
15
20
18
the 5 stations facility layout chart. If
desired output rate is 3600 units/week then calculate the Cycle
time, Idle time, Theoretical minimum (#
of stations) and Efficiency.
Work Stations
A
B
C
D
E
F
G
H
I
Predecessor
-
A
A
B
B
C
C
D, E
F, G
Time (sec)
40
30
50
40
6
25
15
20
18