Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 14,
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 14,
Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 14, 15, and 10, then what is the earliest start time for W? O 10 14 O 15 O cannot be determined