The following estimates of activity times (in days) are available for a small project. Activity Optimistic Most Probable

Posted: Mon May 30, 2022 3:45 pm
by answerhappygod
The Following Estimates Of Activity Times In Days Are Available For A Small Project Activity Optimistic Most Probable 1
The Following Estimates Of Activity Times In Days Are Available For A Small Project Activity Optimistic Most Probable 1 (20.64 KiB) Viewed 17 times
The following estimates of activity times (in days) are available for a small project. Activity Optimistic Most Probable Pessimistic A 5 6.0 7 B 7 8.0 9 с 7 7.5 11.5 D 7 9.0 10 E 6 7.0 9 F 4 5.0 6 (a) Compute the expected activity completion times and the variance for each activity. (Round your answers to two decimal places.) Activity Expected Times Variance A B с D E (b) An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path. (Round your answers to two decimal places.) expected project completion time variance of projection completion time TI