Assume that a project has the following activities and activity times (in months). The project is completed when activit
Posted: Mon May 30, 2022 3:45 pm
Assume that a project has the following activities and activity times (in months). The project is completed when activities F and G are both complete. Activity A B C D E F G Immediate Predecessor A A C, B C, B D, E Time 4 6 2 6 3 3 5 (a) Find the critical path. (Enter your answers as a comma-separated list.) (b) The project must be completed in 1.5 years. Do you anticipate difficulty in meeting the deadline? Explain. The critical path activities require months to complete. Thus the project -Select- be completed in 1.5 years. LL