If we are evaluating two similar projects project A has: NPV $11,000 IRR %16.2 PB 3.4 DPB 3.95 PI 1.04 project B has: NP

Posted: Sun May 29, 2022 5:54 pm
by answerhappygod
If we are evaluating two similar projects
project A has:
NPV $11,000
IRR %16.2
PB 3.4
DPB 3.95
PI 1.04
project B has:
NPV $3,400IRR %19.5PB 2.5DPB 3.43PI 1.09
NPV $3,400
IRR %19.5
PB 2.5
DPB 3.43
PI 1.09
Question: which project should I choose and why?
(From what I know NPV is the best investment appraisa, but in this case do I choose A just because it has higher NPV or project B that has better values for all other criterion?)