Q3: a big western city is requesting federal funding for a park-and-ride project. One of the requirements in the request
Posted: Fri May 27, 2022 7:38 am
Q3: a big western city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Yousif Walker, the chief engineer, wants you to develop a project network plan to meet this requirement. He has gathered the activity time estimates and their dependencies shown here. Draw your project network by AOA method with T box, computing the activity early, late, and slack times. Mark the critical path. Using this legend: (20 marks) Legend of AOA Slack ES LF LS EF ID Description Predecessor Time 5 A None B Survey Soil report Traffic design A 20 с A 30 D A 5 E Lot layout Approve design illumination B, C, D 80+N F E 15 G Drainage E 30 H Landscape E 25 I Signing E 20 Bid proposal F. G, H, I 10 *Ne student's number.