Q3: a big western city is requesting federal funding for a park-and-ride project. One of the requirements in the request
Posted: Fri May 27, 2022 7:15 am
Q3: a big western city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Yousif Walker, the chief engineer, wants you to develop a project network plan to meet this requirement. He has gathered the activity time estimates and their dependencies shown here. Draw your project network by AOA method with T box, computing the activity early, late, and slack times. Mark the critical path. Using this legend: (20 marks) Legend of AOA Slack ES LF LS EF Predecessor None Time 5 Description Survey Soil report Traffic design A 20 A 30 Lot layout A 5 Approve design B, C, D illumination E Drainage E E Landscape Signing E Bid proposal F, G, H, I ID A B C D E F G H I J 81 15 30 25 20 10