Clues: 1- The time unit is weeks 2- Durations are: 1, 2, 3, 4, 5, 6, 7. 3- No two activities have the same duration. 4-

Posted: Thu May 26, 2022 8:45 am
by answerhappygod
Clues 1 The Time Unit Is Weeks 2 Durations Are 1 2 3 4 5 6 7 3 No Two Activities Have The Same Duration 4 1
Clues 1 The Time Unit Is Weeks 2 Durations Are 1 2 3 4 5 6 7 3 No Two Activities Have The Same Duration 4 1 (248.56 KiB) Viewed 10 times
Clues 1 The Time Unit Is Weeks 2 Durations Are 1 2 3 4 5 6 7 3 No Two Activities Have The Same Duration 4 2
Clues 1 The Time Unit Is Weeks 2 Durations Are 1 2 3 4 5 6 7 3 No Two Activities Have The Same Duration 4 2 (362 KiB) Viewed 10 times
Clues:
1- The time unit is weeks
2- Durations are: 1, 2, 3, 4, 5, 6, 7.
3- No two activities have the same duration.
4- There exists only one critical path, and it is the largest possible number given the possible durations shown.
5- The slack times of the seven activities are: 0, 0, 0, 3, 6, 8, 8
6- Activity E has the smallest amount of slack that is greater than zero.
7- The early finish (EF) time for activity A is four weeks, and this does not equal the latest finish (LF) time. (Note: There is no negative slack in the network.)
8- The slack in activity C is eight weeks.
9- The duration of activity F is greater than the duration of activity C by at least two weeks.
Requirements: 1. For each activity calculate: ES, EF, Duration, LS, LF, and Slack. 2. This assignment can be done in a group of four. 3. Make a PowerPoint with animation and explanation to show how you solved the puzzle.
Puzzle: A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown below. B D START A E G END C I