Construct a precedence diagram
Posted: Thu May 26, 2022 8:42 am
Construct a precedence diagram
a) Given in the following table are the task necessary for the assembly of Fine Cedar Chest, the length of time needed to perform each task, and the operations that must be completed prior to subsequent operations. Work Element Precedence Time (min) A None 2 B A 4 с B 5 None D None F C, E, G DEE D F GI G H 531 2 4
a) Given in the following table are the task necessary for the assembly of Fine Cedar Chest, the length of time needed to perform each task, and the operations that must be completed prior to subsequent operations. Work Element Precedence Time (min) A None 2 B A 4 с B 5 None D None F C, E, G DEE D F GI G H 531 2 4