Q1 (a) Safwa Globa Sdn Bhd has been conducted a pavement rehabilitation works at section J35 Jalan Parit Raja to Parit Y
Posted: Sat May 21, 2022 2:57 pm
Q1 (a) Safwa Globa Sdn Bhd has been conducted a pavement rehabilitation works at section J35 Jalan Parit Raja to Parit Yusof, Muar Johor. The issues of weak subgrade was identified and you are responsible to conduct a suitable control test that commonly used to determine the size distribution of fine-grained soils. Discuss with a relevant illustration of a diagram the working principle of it.