CODE ACTIVITY DESCRIPTION TIME (IN HOURS) IMMEDIATE PREDECESSOR(S) A Planning Find location, determine resource requirem
Posted: Sat May 21, 2022 1:32 pm
CODE ACTIVITY DESCRIPTION TIME (IN HOURS) IMMEDIATE PREDECESSOR(S) A Planning Find location, determine resource requirements 20 None B Purchasing Requisition of lumber and sand 60 Planning C ะก Excavation Dig and grade 100 Planning D Sawing Saw lumber into appropriate sizes 30 Purchasing E Placement Position lumber in correct locations 20 Sawing, excavation F Assembly Nail lumber together 10 Placement G Infill Put sand in and under the equipment 20 Assembly H Outill Put dirt around the equipment 10 Assembly 1 Decoration Put grass all over the gordon, landscapo, point 30 Inhill outfit 3. Draw the AON Network. 4. USE CPM to idnetify the critical path. 5. What is the total completion time? 6. What is the slack time of any and all noncritical paths through the project?