The following information belongs to a target cost contract: Target cost = $250 M Target band = $230 M and ends $270 M T

Posted: Sat May 21, 2022 12:49 pm
by answerhappygod
The Following Information Belongs To A Target Cost Contract Target Cost 250 M Target Band 230 M And Ends 270 M T 1
The Following Information Belongs To A Target Cost Contract Target Cost 250 M Target Band 230 M And Ends 270 M T 1 (33.77 KiB) Viewed 18 times
The following information belongs to a target cost contract: Target cost = $250 M Target band = $230 M and ends $270 M Target contractor fee = $10.5 M Cost saving share = 55/45 by owner Cost increase share = 65/35 by contractor Contractor minimum fees =$5 M The GMC = $320 M Minimum expected project cost = $ 200 M ?Calculate the contractor maximum fee إختر أحد الخيارات: M42 .a M 27 .b M 39 .c M 24 d