For a manufacturing line, the data below on the task precedence relationships exist Task Performance time (min) Must Fol
Posted: Sat May 21, 2022 9:39 am
by answerhappygod

- For A Manufacturing Line The Data Below On The Task Precedence Relationships Exist Task Performance Time Min Must Fol 1 (43.9 KiB) Viewed 9 times

- For A Manufacturing Line The Data Below On The Task Precedence Relationships Exist Task Performance Time Min Must Fol 2 (19.77 KiB) Viewed 9 times
For a manufacturing line, the data below on the task precedence relationships exist Task Performance time (min) Must Follow A 3 B 6 A С 7 A D 2 A E 2 A F 4 C, B G 5 с H 5 D, E, F, G Compute the minimum cycle time?
What is the minimum number of workstations and the corresponding line efficiency? can we increase the production rate?