Page 1 of 1

5) Coolant circulation pump X for continuous operation in a nuclear power station has MTBF = 2 yrs. and MTTR = 10 hrs. A

Posted: Fri May 20, 2022 10:29 pm
by answerhappygod
5 Coolant Circulation Pump X For Continuous Operation In A Nuclear Power Station Has Mtbf 2 Yrs And Mttr 10 Hrs A 1
5 Coolant Circulation Pump X For Continuous Operation In A Nuclear Power Station Has Mtbf 2 Yrs And Mttr 10 Hrs A 1 (23.02 KiB) Viewed 11 times
5) Coolant circulation pump X for continuous operation in a nuclear power station has MTBF = 2 yrs. and MTTR = 10 hrs. A standby older pump Y with the same capacity is also used with MTBF = 22 mo. and MTTR = 15 hrs. Perfect switching between pumps A and B of the plant is assumed. (0) Draw the detailed Markov process graph of the cooling pump system and determine the limiting (steady-state) probability of all states that it is possible to find the system in. (II) What is the availability of the nuclear station's pumping system?