Page 1 of 1

Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME (days) MO

Posted: Fri May 20, 2022 3:27 pm
by answerhappygod
Consider The Following Precedence Chart Activity Preceding Activities Optimistic Time Days Pessimistic Time Days Mo 1
Consider The Following Precedence Chart Activity Preceding Activities Optimistic Time Days Pessimistic Time Days Mo 1 (52.35 KiB) Viewed 24 times
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME (days) MOST LIKELY TIME (days) 10 A 5 |15 B 10 12 14 C 10 10 D B.C 10 4 2 16 E А 4 12 IF 18 8 4 12 А DE F 10 14 12 18 4 G 12 16 2 14 The total slack for activity Cis O 2 ОО 8 4