[phpBB Debug] PHP Warning: in file [ROOT]/ext/lmdi/autolinks/event/listener.php on line 237: Undefined array key 34
[phpBB Debug] PHP Warning: in file [ROOT]/ext/lmdi/autolinks/event/listener.php on line 237: Trying to access array offset on value of type null
Answer Happy • Question 5 20 Points The following is a project schedule showing tasks along with their durations: 120 Marks] Activity P
Page 1 of 1

Question 5 20 Points The following is a project schedule showing tasks along with their durations: 120 Marks] Activity P

Posted: Fri May 20, 2022 12:23 pm
by answerhappygod
Question 5 20 Points The Following Is A Project Schedule Showing Tasks Along With Their Durations 120 Marks Activity P 1
Question 5 20 Points The Following Is A Project Schedule Showing Tasks Along With Their Durations 120 Marks Activity P 1 (26.28 KiB) Viewed 59 times
Question 5 20 Points The Following Is A Project Schedule Showing Tasks Along With Their Durations 120 Marks Activity P 2
Question 5 20 Points The Following Is A Project Schedule Showing Tasks Along With Their Durations 120 Marks Activity P 2 (13.61 KiB) Viewed 59 times
Question 5 20 Points The Following Is A Project Schedule Showing Tasks Along With Their Durations 120 Marks Activity P 3
Question 5 20 Points The Following Is A Project Schedule Showing Tasks Along With Their Durations 120 Marks Activity P 3 (13.61 KiB) Viewed 59 times
Question 5 20 Points The following is a project schedule showing tasks along with their durations: 120 Marks] Activity Predecessor Duration (Days) A NONE 4 B NONE 5 с A, B 8 D С 1 E с 2 F DE 3 G E 4 H F G 6

Slack of all (EF). Finish (LF) and 1) Construct the Activity Network Diagram. 2) Find Early Start (ES) Early Finish activities 3) Find the Critical Path 4) Find the project duration [4 Marks) Late Start (LS). Late [8 x 15 = 12 Marks) [2 marks] [2 marks)