Question 5 20 Points The following is a project schedule showing tasks along with their durations: 120 Marks] Activity P
Posted: Fri May 20, 2022 12:23 pm
Question 5 20 Points The following is a project schedule showing tasks along with their durations: 120 Marks] Activity Predecessor Duration (Days) A NONE 4 B NONE 5 с A, B 8 D С 1 E с 2 F DE 3 G E 4 H F G 6
Slack of all (EF). Finish (LF) and 1) Construct the Activity Network Diagram. 2) Find Early Start (ES) Early Finish activities 3) Find the Critical Path 4) Find the project duration [4 Marks) Late Start (LS). Late [8 x 15 = 12 Marks) [2 marks] [2 marks)
Slack of all (EF). Finish (LF) and 1) Construct the Activity Network Diagram. 2) Find Early Start (ES) Early Finish activities 3) Find the Critical Path 4) Find the project duration [4 Marks) Late Start (LS). Late [8 x 15 = 12 Marks) [2 marks] [2 marks)