Page 1 of 1

Question 4 Calculate the amount assigned to each task in the following WBS. [16x 1 = 16 Marks] Total project cost $500.0

Posted: Fri May 20, 2022 12:21 pm
by answerhappygod
Question 4 Calculate The Amount Assigned To Each Task In The Following Wbs 16x 1 16 Marks Total Project Cost 500 0 1
Question 4 Calculate The Amount Assigned To Each Task In The Following Wbs 16x 1 16 Marks Total Project Cost 500 0 1 (39.68 KiB) Viewed 36 times
Question 4 Calculate the amount assigned to each task in the following WBS. [16x 1 = 16 Marks] Total project cost $500.000 Design 20% Program 30% Tost 40% Document 5% Produce CD 5% D-1 10% D-2 10% P-1 20% P-2 5% P3 5% Doc-1 2% Doo 2 3% CD-1 5% T: 1 10% T-2 10 T-3 20%