The route sheet for a handle used in medical diagnostic equipment is given in Table 2.5. Also given are the desired dail
Posted: Fri May 20, 2022 9:43 am
Company, Inc., must purchase if the production rate at the lathe, drill, knurl, and buff is 6, 10, 15, and 18 units per hour respectively. Each day includes 8 working hours. TABLE 2.5 Production Data for Mediquip Co., Inc., in Exercise 9 Part Name: Handle Prepared by SSH Oper Code Machine Code Machine Name Required Output Scrap Rate (%) 10 2053 Lathe 103 5 20 1226 Drill 100 8 30 3029 Knurl 100 12 3007 Buff 100 10 40
The route sheet for a handle used in medical diagnostic equipment is given in Table 2.5. Also given are the desired dailyoutput and scrap rate for each machine. Assuming that each machine has 90% manufacturing efficiency, determine (1) the required input and (2) how many machines of each type Mediquip