Equity raised for the project: ₹60 lakhs ,Debt taken: ₹30 lakh ,Cost of debt kd= 8% ,Cost of equity ke : 18% Calculate t

Posted: Tue Nov 23, 2021 8:50 am
by answerhappygod
Equity raised for the project: ₹60 lakhs ,Debt taken: ₹30 lakh
,Cost of debt kd= 8% ,Cost of equity ke : 18%
Equity Raised For The Project 60 Lakhs Debt Taken 30 Lakh Cost Of Debt Kd 8 Cost Of Equity Ke 18 Calculate T 1
Equity Raised For The Project 60 Lakhs Debt Taken 30 Lakh Cost Of Debt Kd 8 Cost Of Equity Ke 18 Calculate T 1 (10.51 KiB) Viewed 118 times
Calculate the cost of capital for the project
Cost of Capital The details of a project are: Equity raised for the project: +60 lakhs Debt taken: 30 lakh Cost of debt (ka): 8% Cost of equity (ke): 18% Calculate the cost of capital for the project. 12.88% 14.67% 11.57% 15.25%