Page 1 of 1

NETWORK DIAGRAM - PART 1 Consider the following information about a project: Activity Duration (days) Predecessors А. 10

Posted: Fri May 20, 2022 8:23 am
by answerhappygod
 1
1 (34.4 KiB) Viewed 44 times
NETWORK DIAGRAM - PART 1 Consider the following information about a project: Activity Duration (days) Predecessors А. 10 B 9 A С 20 A D 17 B.C E 16 D F 9 с G 10 F H 6 E, G After creating a complete two pass Network Diagram for this project in a sheet of paper with your name, answer how much is the total duration of this project in days?