Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the

Posted: Fri May 20, 2022 8:19 am
by answerhappygod
Ross Hopkins President Of Hopkins Hospitality Has Developed The Tasks Durations And Predecessor Relationships In The 1
Ross Hopkins President Of Hopkins Hospitality Has Developed The Tasks Durations And Predecessor Relationships In The 1 (31.22 KiB) Viewed 90 times
e) the activity variance along the critical path is ____
weeks. (round response to two decimal places)
f) the probability that Hopkins Hospitality will finish the
project in 36 weeks or less is ____. (enter as a probability and
round your response to three decimal places)
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) a m Activity А B С D E F Time (weeks) a m b 6 8 12 1 9 23 9 12 16 5 6 9 1 3 4 5 9 21 Immediate Predecessor(s) Activity G A Н. A I А J B K C, E 2 2 5 6 1 3 2 5 8 1 b 4 2 5 12 4 Immediate Predecessor(s) C, E F F D, G, H 1,J a) The expected (estimated) time for activity C is 12.17 weeks. (Round your response to two decimal places.) b) The variance for activity C is 1.36 weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A-B-E-F-H-J-K. d) The estimated time for the critical path is weeks. (Round your response to two decimal places.)