18. Please crash the following project to 25 days: Normal Crashed Duration Cost Duration Cost Activity (days) (AZN) (day

Posted: Fri May 20, 2022 7:55 am
by answerhappygod
18 Please Crash The Following Project To 25 Days Normal Crashed Duration Cost Duration Cost Activity Days Azn Day 1
18 Please Crash The Following Project To 25 Days Normal Crashed Duration Cost Duration Cost Activity Days Azn Day 1 (30.4 KiB) Viewed 37 times
18. Please crash the following project to 25 days: Normal Crashed Duration Cost Duration Cost Activity (days) (AZN) (days) (AZN) A* 3 2 1,500.00 2,000.00 B 5 4 3,500.00 5,000.00 C 4 3 6,800.00 7,500.00 D 5 3 2,500.00 6,000.00 E 7 6 6 4,200.00 5,400.00 F 4 3 2,000.00 2,700.00 28 21 28,600.00 Total 20,500.00 Crash the project by 3 days with minimal cost: 1. Calculate the cost of crashing per day of each activity 2. Identify - which activities should be crashed? 3. Calculate - what will be the cost of crashing the project by 3 days? 4. Calculate - what will be the cost of the crashed project? (*) - yellow is a critical path activity