Q3. [33 pts. Given the network plan below, develop a loading chart for resources (Electrical Engineers (EE), Mechanical
Posted: Fri May 20, 2022 7:27 am
Q3. [33 pts. Given the network plan below, develop a loading chart for resources (Electrical Engineers (EE), Mechanical Engineers (ME)) using trial and error approach. Assume that only one of each resource exists at each time period. a) For the schedule obtained in (a), compute the early, late, and slack times for your project. Define the new critical activities and project duration ME 02 EE 4 6 ME 2 (End). 7 EE Develop a loading schedule for each resource below. (Figure 8.3) EE ME 9 11 Legend ES ID EF Fill in the times below for a resource activity schedule ID/RES ES LS EF LF SL 1EE 2-EE 3.ME 3.ME ALE 4.EE 5-ME 6-ME 7-EE LS OURALE Resource