activity Predecessor Duration Budget % Completion Actual Actual Cost (AC) A 4 40 100 35 B 5 32 100 24 C A 4 48 100 32 D
Posted: Fri May 20, 2022 7:15 am
activity Predecessor Duration Budget % Completion Actual Actual Cost (AC) A 4 40 100 35 B 5 32 100 24 C A 4 48 100 32 D A,B 5 18 33 20 E В. 3 28 100 20 F C,D,E 2 40 0 o A. B. What is the cost performance index (CPI)? What is the schedule performance index (SPI)? What is the estimated additional cost for completing the project? What is the estimated project cost at completion? دان