Q2: The activities involved in the construction of a certain project are given in the table below. One resource type wil
Posted: Fri May 20, 2022 6:55 am
Q2: The activities involved in the construction of a certain project are given in the table below. One resource type will be used during the contract. It is required to schedule the project above so that the daily resource requirements do not exceed 3 labours. (15 degrees) 1- Total project finishing time (2 marks) 2- Critical path diagram (2 marks) 3- Resources bar chart (5 marks) 4- Resources scheduling (6 marks) S Activity Description Dependency Duration (Days) Number of Labours المدة بالأيام الاعتمادية أو الفعاليات السابقة وصف الفعالية عدد العمال باليوم الواحد 1 2 3 4 5 6 A B с D E F A A A C&D B&E 3 5 5 4 2 3 (Unit/Day) 3 2 1 2 3 2