Al Khaleej Inc. needs 410 kgs of a material per month. It costs RO 100 to make and receive an order, and it takes 12 wor
Posted: Fri May 20, 2022 6:32 am
company is operating 6 workdays per week in a 52-week year. What is the expected time (in weeks) between order? Round-up to the nearest integer Select one: a. 100 b. 115 c. None is correct d. 111
Al Khaleej Inc. needs 410 kgs of a material per month. It costs RO 100 to make and receive an order, and it takes 12 workdays to receive it. The annual holding cost is 20 % of purchase price. The price RO 2 per kg. The