Al Khaleej Inc. needs 410 kgs of a material per month. It costs RO 100 to make and receive an order, and it takes 12 wor

Posted: Fri May 20, 2022 6:32 am
by answerhappygod
Al Khaleej Inc Needs 410 Kgs Of A Material Per Month It Costs Ro 100 To Make And Receive An Order And It Takes 12 Wor 1
Al Khaleej Inc Needs 410 Kgs Of A Material Per Month It Costs Ro 100 To Make And Receive An Order And It Takes 12 Wor 1 (59.2 KiB) Viewed 58 times
Al Khaleej Inc. needs 410 kgs of a material per month. It costs RO 100 to make and receive an order, and it takes 12 workdays to receive it. The annual holding cost is 20 % of purchase price. The price RO 2 per kg. The company is operating 6 workdays per week in a 52-week year. What is the expected time (in weeks) between order? Round-up to the nearest integer Select one: a. 100 b. 115 c. None is correct d. 111